Rob requested 3 quotes from Excavation Experts in Morang South
					  Need approx 200 cubes of dirt removed.
* Top 700mm is subsoil.
* Bottom 1300 is dense clay.
***No rock at all.***
I think a 5 ton excavator would fit, theres around 3.5 metres clearance between house and fence.
In summary, its approximately 2 metres of fall over 28 metres.  Width is 2 metres at one side, 5 at the end.
I need this job completed within 2 weeks, the sooner the better.   Give me a call/email and i can send you a picture or you can come out and have a look.
It my intention to build 1 or 2 sleeper retaining walls against this dig.
				
Kelgar Minidiggers and Garden Services
Transform Landscaping
Andy Handy
	DIRT TO BE DUG UP AND REMOVED  PRIVATE PREMISES -
	DIRT TO BE DUG UP AND REMOVED  PRIVATE PREMISES - FEW TRUCK LOADS OF DIRT
	Excavation for a 12x12 meter shed and level out some other areas
	Require excavation ASAP for a 12x12 meter shed and a seperate area levelled...
	Dirt Excavation and removal
	front of house, approximately 25sqm.  200mm deep and removal.
	Excavation - Clean fill provided and bobcatted in
	I require some clean fill to be provided and bobcatted into place. Access is...