John Metcalf requested 3 quotes from Construction & Property Services Experts in Yarrawonga via BUILD
*Yarrawonga College "Jnr School" (Project Stage 1)
*2 No. Proposed buildings = Classrm bldg & Admin bldg (both single level)
*Exist. clear greenfield site - has easy access & flat terrain with negligible slope/run-off.
*Struc Design Engineers (Perrett Simpson Stantin) has proposed the conc slabs to be founded on "lightly compacted raised 'fill' platforms" (to assist improvement of drainage/rainwater run-off)
*Above requires "70kN capacity Steel Screw Piles" installed as follows:
(i) Supply/install 502 no. screw piles to Classrm Bldg (1630m2 slab GFA)
(ii) Supply/install 212 no. screw piles to Admin. Bldg (690m2 slab GFA)
*All up = Total "714 No." Screw Piles under Total "2,320m2" slab GFA (Gross Floor Area)